Chiquola Mill Week 1 Update - May 4 – May 8, 2026
Chiquola Mill Week 1 Update - May 4 – May 8, 2026
While the rain was much needed, it unfortunately began shortly after work started on site. Ben provided the following construction update yesterday:
- Vegetation clearing around the pond is approximately 90% complete.
- Erosion control installation remains in progress and is on schedule to be completed adjacent to the pond by Monday.
- One row of silt fence has been installed along the lower portion of the site, with portions of the second row also completed.
- Erosion control (silt fence) along lower portion of site under construction and mostly complete.
- Vegetation removal was started along lower portion of the site with 90% cleared around pond.
- Excavation of one sediment trap began this week. During excavation, crews encountered brick and concrete debris. The affected soil and material are being stockpiled for proper disposal at a later date.
- Pond backfill is expected to be completed on or around May 15.
- Removal of asbestos-containing building debris near the parking lot is scheduled to begin Monday around noon.
- Additional asbestos debris near the upper area of the pond is also scheduled for removal next week.
- Approximately 3,200 tons of asbestos debris are expected to be removed next week.
We appreciate everyone’s patience as work continues and will provide additional updates as progress continues.
Community Meeting Recap: Pre-Construction Meeting Held
Chiquola Mill Project Pre-Construction Meeting Held
On Monday, May 4, community leaders and project partners gathered for the Chiquola Mill Project Pre-Construction Meeting, marking an important milestone in the revitalization of this historic site.
Mayor Jimmy Smith, Administrator Larry Young, and Sam Gilmer were joined by members of the Stantec Project Team, Goldman Site Services, LLC, and the Maher’s office to discuss next steps and coordinate efforts ahead of construction.
This meeting represents continued progress toward transforming the Chiquola Mill property into a space that will serve and strengthen the community for years to come. The collaboration among local leadership and project partners reflects a shared commitment to thoughtful development and long-term investment in the area.
Chiquola Mill Week 2 Update - May 11 - May 15, 2026
Chiquola Mill Week 2 Update - May 11– May 15, 2026
- 700 tons of Asbestos Containing Materials were removed from the site and disposed of at the Anderson Regional Landfill
- A portion of the standing structure was demolished and demolition activities will continue this week on the elevator shaft and surrounding standing structure.
- The former mill pond has been 90% filled and the surrounding area has been graded and sloped to promote minimal runoff.
- Erosion control containment on the pond side of the mill has been completed with check dams.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 3 Update - May 18 - May 22, 2026
Chiquola Mill Week 3 Update - May 18– May 22, 2026
Chiquola Mill Week 3 Update – May 18– May 22, 2026
- Structures along the mill side of the pond were located beneath vegetation and debris piles and removed as part of the pond backfilling and grading activities
- The first of three sediment traps were installed on the lower side of the mill as part of the erosion control activities
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
- Vegetation clearing activities began on the west side of the site along Chiquola Avenue
- 1,240 tons of Asbestos Containing Materials were removed from the site and disposed of at the Anderson Regional Landfill
Chiquola Mill Week 4 Update - May 25- May 29, 2026
Chiquola Mill Week 4 Update - May 25– May 29, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of May 22 – 26, 2026.
- Project activities were impacted in the early part of the week due to the Memorial Day holiday and heavy rainfall in the area.
- 1,274 tons of Asbestos Containing Materials were removed from the site and disposed of at the Anderson Regional Landfill.
- The former elevator shaft portion of the standing structure was demolished, with the remaining portion slated for demolition next week.
- Vegetation clearing and erosion control activities began along the Chiquola Avenue side of the site.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 5 Update - June 1 - June 5, 2026
Chiquola Mill Week 5 Update - June 1 - June 5, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of June 1 – 5, 2026.
- The remaining standing mill structures have been an eyesore for the community for the last 15 years. Last week, those structures were demolished, have been cleared from the property, and disposed of at the Anderson Regional Landfill.
- 1,828 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Through Friday, June 5th a total of 5,042 tons of Asbestos Containing Materials have been removed from the property.
- Erosion control, vegetation clearing and removal of debris continued along the Chiquola Avenue side of the property.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 6 Update - June 8 - June 12, 2026
Chiquola Mill Week 6 Update - June 8 - 12, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of June 8 – 12, 2026.
- Removal activities continued around the mill footprint and along Chiquola Avenue.
- 1,823 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Demolition of concrete slab above basement area was started and will continue next week.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 7 Update - June 15 – June 19, 2026
Chiquola Mill Week 7 Update - June 15 – June 19, 2026.
Provided below is an update on the project activities at the Chiquola Mill for the week of June 15 – 19, 2026.
- Demolition and removal of basement area continued during the week as well as clearing of debris around the footprint of the building.
- 1,491 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 8 Update - June 22– June 26, 2026
Chiquola Mill Week 8 Update - June 22– June 26, 2026.
Provided below is an update on the project activities at the Chiquola Mill for the week of June 22 – 26, 2026.
- Vegetation and debris removal continued along Chiquola Avenue and rear parking lot along Beacham Street.
- Vegetation is being mulched for spreading on the property as part of erosion control measures.
- 1,266 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 9 Update - June 29– July 3, 2026
Chiquola Mill Week 9 Update - June 29 - July 3, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of June 29 – July 3, 2026.
- Vegetation and debris removal activities along Chiquola Avenue were completed.
- Additional silt fencing was installed along Chiquola Avenue as part of erosion control measures.
- 1,200 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 10 Update - July 6– July 10, 2026
Chiquola Mill Week 9 Update - June 29 - July 3, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of July 6 – 10, 2026.
- Excavation and consolidation of remaining debris across a large portion of the site was completed.
- 1,786 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Grading and sloping activities continued across the lower portion of the site in preparation for seed and straw.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 11 Update - July 13 – July 17, 2026
Chiquola Mill Week 11 Update - July 13 - 17, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of July 13 – 17, 2026.
- Excavation and consolidation of debris continued across the central portion of the property.
- 912 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- The second row of silt fence was installed along Chiquola Avenue.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 12 Update - July 20 - July 24, 2026
Chiquola Mill Week 12 Update - July 20- 24, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of July 20 – 24, 2026.
- Removal of Asbestos-Containing Materials has slowed over the previous two weeks due to less overall debris onsite and heavy rainfall.
- 767 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 13 Update - July 27- July 31, 2026
Chiquola Mill Week 13 Update - July 27- 31, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of July 27 – 31, 2026.
- 1,031 tons of Asbestos-Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 14 Update - August 3- August 7, 2026
Chiquola Mill Week 14 Update - August 3- 7, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of August 3 – 7, 2026.
- 1,369 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 15 Update - August 10- August 14, 2026
Chiquola Mill Week 15 Update - August 10- 14, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of August 10 – 14, 2026.
- Cleanup activities have focused on the removal of the final debris piles and concrete slabs and footers.
- 2,327 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.
Chiquola Mill Week 16 Update - August 17 - August 21, 2026
Chiquola Mill Week 16 Update - August 17 - 21, 2026
Provided below is an update on the project activities at the Chiquola Mill for the week of August 17 – 21, 2026.
- Cleanup contractor continued work on the removal of the remaining debris piles and concrete slabs and footers.
- 1,507 tons of Asbestos Containing Materials were removed from the property and disposed of at the Anderson Regional Landfill.
- Stormwater/erosion control weekly inspections are being completed by Stantec to ensure compliance with the approved stormwater plan.

Community Meeting Recap: Chiquola Mill Cleanup
Community members gathered on Tuesday, April 28 at 6:00 PM for the Chiquola Mill Cleanup Public Notice pre-cleanup meeting. The meeting provided an opportunity to discuss upcoming steps and share important information about the project.
Honea Path, SC – April 22, 2026 – The Town of Honea Path is pleased to announce the launch of weekly online updates for the Chiquola Project, now available on the Town’s official website and social media platforms.
As part of an ongoing commitment to transparency and community engagement, these updates will provide residents with regular insights into the progress, milestones, and developments related to the Chiquola Project. The initiative aims to keep the public informed and involved as work continues.
Town officials, in collaboration with project partners, will share detailed updates, along with photos and highlights, to give the community a clear view of the project as it moves forward.
Residents are encouraged to visit the Town of Honea Path website and follow official social media pages to stay up to date with the latest information. For more information, please contact info@honeapathsc.com.

Stantec
DAVID SYKES
Brownfields Project Manager
803-604-6013
david.sykes@stantec.com
Goldman Site Services, LLC
BEN GOLDMAN
President
843-687-2795
goldmansservices@outlook.com
South Carolina Department of Environmental Services
CHRIS KAIBERY, P.G.
Brownfields Project Manager
803-898-0924
christopher.kaibery@des.sc.gov
U.S. Environmental Protection Agency
AUSTIN GILLY
Brownfields Project Manager
678-640-2306
gilly.austin@epa.gov
MAYOR JIMMY SMITH
mayor@honeapathsc.com
SAM GILMER – MEDIA
sgilmer@honeapathsc.com
LARRY YOUNG – TOWN ADMINISTRATOR
lyoung@honeapathsc.com